Solar Process

Site Survey: 

Call to schedule site survey within 3 days of contract signing. Panel Layout Approval: Customer approved panel layout. HOA approved panel layout (if required).

·         Design/Engineer Package: 

Permit Engineering package will be ordered including structural and electrical stamp (if necessary); typically takes 2-7 days.

·         Installation Permit

Permit application may take 5 - 30 days.

 Installation Schedule: 

Project Coordinator will schedule installation appointment and double confirm prior to installation. Installation typically takes 2 days on a standard installation. If required, Main Service Panel upgrade (MPU) will take longer.

·         Monitoring: 

Set up account during inspection for solar system monitoring.

·         Inspection: 

Project coordinator will coordinate with the building department and utility company to schedule solar installation inspection.

·         PTO: 

Permission to Operate / Interconnection Approval will be filed by Discounted Solar.


Solar Installation Company: Sacramento Rocklin El Dorado Hills Lincoln Carmicheal Orangevale Auburn Placerville Yuba City Wheatland Chico Elk Grove Lodi Stockton Turlock Modesto Fresno Lodi Galt Granite Bay Loomis Newcastle Whitney Oroville Sheridan Cameron Park Pleasant Grove Woodland Davis Vacaville